We’ve had an update on the Hopkinton Main Street Corridor Project. What used to be weekly updates have been a bit more sporadic and Project Managers say the weeklies will resume at some point but for now it is just “as needed”. They say Comcast, AT&T, and Comm-tract are on track to finish work this month despite Comcast having a delay. Verizon will be on site this week to transfer some equipment and install new fiber. As for landscaping they say there were some changes which are under review by MassDOT.
Loading advertisement…
Current Weather

As of 4:25 am
40°Clear
- Humidity
- 81%
- Dew point
- 33°
- Wind
- NW 7 mph
- Visibility
- 10 mi
- Pressure
- 30.27 in
- TodayHigh 54° 0% chance of rain
- TonightLow 29° 0% chance of rain
- SunHigh 60° 0% chance of rain
- Sun NightLow 41° 0% chance of rain
- MonHigh 67° 0% chance of rain
Upcoming Events
Haunted Market
Now - Sat, Oct 31 at 9:00pm
A Touch of Magick
Annual Halloween Nail Trimming Event
Sat, Oct 31 at 9:00am
Stanley Mill Antiques
Franklin’s Not So Scary Halloween Party
Sat, Oct 31 at 10:30am
Franklin Public Library
Taste of Bellingham
Wed, Nov 4 at 6:00pm
Bellingham High School
Indigenous Past, Present, And Future
Fri, Nov 6 at 6:30pm
Upton Community Center