In a big step forward for the Hopkinton Main Street Corridor Project, project managers say Eversource has completed all of its overhead and underground work and have started to remove their old overhead lines in the underground section of the project from the Police Station to Ash Street. Comcast is now undergrounding their lines there. Once they are done, Verizon will come in and remove the utility poles.