HOPKINTON – Progress continues on the Hopkinton Main Street Corridor Project, with Verizon expected to complete all utility transfers by the end of this month.
Project officials say the paving contractor has been coordinating with Verizon and Eversource to work around manholes and other utility structures. Town officials report that final paving on the west side of the project could begin within the next couple of weeks.
In addition, all trees from Weston Nurseries have arrived, and landscapers are scheduled to begin planting this week.