Final Transformers for Hopkinton Main Corridor Project Arrive

SHARE NOW

By MyFM’s Claire Beverly – The final six transformers needed for Hopkinton’s Main Corridor Project have arrived and are now in the testing phase by Eversource. In their weekly update on the project the town says the first three of the very long-awaited transformers were installed July 25 and while they have not given a full schedule for the rest of their installation, they say there are no issues anticipated. Also this week, they continue with the overhead utility line transfers, and there will be brickwork mockup done in front of Town Hall.