All Delayed Transformers Installed for Hopkinton Main Street Project

SHARE NOW

By MyFM’s Claire Beverly – All 12 of the long-delayed electric transformers for the Hopkinton Main Street Corridor Project have been installed. Project Managers say Eversource crews are working on the preliminary work associated with the transformers which would be done within the next month and the start of moving from overhead to underground should begin in late September or early October. The delivery of the transformers was delayed nearly two years due to a global shortage but they started arriving in Hopkinton last month.